SH39 SYMES BRIDGE SUPERSTRUCTURE REPLACEMENT

Client

NZTA

Scope

Bridges
Complex Structures
Roading

Partners

BECA, Pollock Cranes, Preco
We were engaged by NZTA to replace the superstructure of Symes Bridge on SH39 over the Moakurarua Stream, following erosion damage in the February storm. The works delivered a wider, more resilient crossing on a key rural route, with the road closure programmed for seven weeks and completed in five.

The existing superstructure was removed and replaced with a new 38m, three-span structure of steel girders and six precast deck panels, the heaviest weighing 59 tonnes, installed over the stream using a 600T mobile crane. An early-strength concrete mix was used for the deck stitch pour, enabling the road to reopen sooner. The piers were also strengthened with stressbars and new bearings.

To minimise the closure, SH39 was fully closed rather than managed through staged traffic switches, and all steelwork was shop-fabricated off-site to remove on-site welding from the critical path. We worked closely with BECA to resolve buildability details ahead of construction. Existing services were temporarily supported and relocated onto the new deck, and students from Ngutunui School were invited to watch the main crane lift.

Works in and adjacent to the stream were carried out under resource consent conditions, with erosion and sediment controls in place and rock revetment and reno mattress scour protection installed along both banks.

The project was completed 1.5 weeks ahead of programme.

No items found.
No items found.
No items found.
No items found.

Discover more

Discover more