St Lukes Cycleway Safety Improvements

Client

NZTA

Scope

Cycleways/Boardwalks
Roading

Partners

Auckland Transport, Parallaxx, GHD
This project enhanced safety for one of Auckland’s busiest cycleway crossings, requiring complex traffic management across motorway ramps, pedestrian pathways, and key intersections. The works included constructing a new cycle lane, five raised speed tables, footpath realignment, stormwater upgrades, and repositioning street lighting and signals.

To meet NZTA’s urgent timeline, we implemented 24/7 construction with “super weekends”, optimising lane closures and minimising disruptions. Our detailed TTM planning, stakeholder engagement, and accelerated construction programme ensured completion within four weeks, successfully improving cyclist and pedestrian safety.

No items found.
No items found.
No items found.
No items found.

Discover more

Discover more