We proposed an alternative deck design of FRP decking on a timber substructure, supported on 38 screw piles. The lighter structure avoided concrete demolition, retained the heritage kerb with the deck set to kerb level, and was tapered into the existing bridge at each end rather than removing it.
Following our delivery of the Heather Street Boardwalk, we mobilised within two weeks of award. Works were carried out in a live CBD street under traffic management, with local businesses and residents engaged before work started and the site coordinated around a filming event mid-construction.
The screw piles required no excavation and kept vibration well below the heritage limit, with the bluestone kerb and stone retaining wall protected throughout.
โ