Works were sequenced progressively, allowing the structures contractor to commence early, mitigating the impact of unforeseen delays. Traffic and congestion challenges were managed through detailed staging diagrams, 3D modelling, and a coordinated site access system, optimising truck movements and minimising disruption in Auckland’s busy CBD environment.
The project required smart retaining solutions, including soldier piles, soil nails, and temporary shotcrete walls, while also navigating archaeological discoveries that triggered a two-month site shutdown.